  • Geopier foundation work was completed on Friday, July 9th. The geopier equipment is being hauled out now. 
  • The building's fire service and water service are going out for redesign. 
  • The excavation work for the foundation has started. In about two weeks, the footers will be put in and concrete will be poured. 
  • The materials for the storm detention system are on order and some have already been received. 
  • An image of the project schedule was shared. It can be seen below. 
  • Laura St. between Clinton St. and Cora St. has been turned into a one-way street going northbound. A discussion took place about removing the one way signs located on Clinton St., since they are not needed in their current spots. An idea has been floated about signing the corner of Charles St. and Laura St. to prevent vehicles from turning onto Laura St. and then having to turn around at the "Do Not Enter" sign. 
  • The next construction update meeting will be on Wednesday, July 28th at 5:30 p.m.
  • Contact info:
    • Brian Kail - 970-596-7147, brian@strykerco.net 
    • Mark Clutts - 970-901-6220, mark@strykerco.net
    • Preston Neill - 970-318-0081, pneill@town.ridgway.co.us