S2C Construction Updates - August 25, 2021

Image
Attendees: Brian Kail, Stryker & Company Mark Clutts, Stryker & Company Leo Perez, Stryker & Company Diedra Silbert, Town of Ridgway Preston Neill, Town of Ridgway The crew has been making great progress, highlighted by stair tower B going up.  The crew will start pouring all the foundations around stair tower A and then backfilling by the end of the week.  The masons will move from stair tower B to stair tower A late next week.  Stryker is planning to meet with reps from SMPA to discuss the electrical work that needs to be done, as well as the boxes that need to be laid in the right-of-way.  Stryker explained that a series of street and alley closures will be needed for various work in the Town right-of-way. Brian Kail said Stryker will soon begin communicating with area residents about these closures (with Town assistance), including timelines and impacts. Below is a list of durations for installing the storm water underground piping from Charles St. up Cora St. down the

S2C Construction Updates - August 12, 2021

Image
Attendees: Brian Kail, Stryker & Company Diedra Silbert, Town of Ridgway Preston Neill, Town of Ridgway The crew has been working on Stair tower B, which is located in the northeast corner, and they are getting ready for laying the underground utilities. Backfill will start going in on Tuesday, August 17th.  The footers have been laid out over at Stair tower A, which is located in the southeast corner. Forming will start on Monday, August 16th. Then, the crew will prepare to place concrete and get the walls erected.  The structures for the storm water system will be installed very soon. A plan will be developed next week to go about installing the water detention/sub-surface manifold, the storm detention box, and other materials. Storm pipes will be installed running east down the alley. Notices will be put out to area residents informing them of the upcoming work of storm water system installment and the need to close the alley. The aim is to provide a two week notice.  A Revocabl