S2C Construction Updates - June 30, 2021

 

Topic: Bi-Weekly Space to Create Project Update with Stryker & Company       
Join Zoom Meeting
https://us02web.zoom.us/j/81166252778?pwd=VEIvVWZOYllwSXY5ajRBZzhralY2UT09 
Meeting ID: 811 6625 2778
Passcode: 778450
Dial by your location
        +1 346 248 7799 US 
        +1 312 626 6799 US

  • Attendees:
    • Mark Clutts, Stryker & Company
    • Leo Perez, Stryker & Company
    • Liz Teitz, Ouray County Plaindealer
    • Matt McIsaac
    • Cat Lichtenbelt
    • Preston Neill, Town of Ridgway
    • Diedra Silbert, Town of Ridgway
    • Andrew Michaelson, Artspace
  • Geopier foundation work, which was supposed to take place the week of June 21st, will begin tomorrow (July 1st). Excavation equipment has already mobilized on the site. Gravel we be compacted into the ground and the work will be loud. There is also a good deal of vibration that comes with this type of work but it should not be felt more than 20 feet away from the hole. 
  • Aggregate is being imported to the site. This will be happening through next week.
  • Once the geopier foundation work is complete, Stryker will work on prepping the building pad. Then, they will start working on the fire suppression service tie-in. 
  • Stryker is still waiting on a traffic signage plan from the traffic control planner they are working with. Once it's received, it will be shared with the Town. 
  • The Town has been working with Stryker on making Laura St. between Clinton St. and Cora St. a one-way street going northbound. The one-way traffic signage is slated to go up tomorrow (July 1st). 
  • The next construction update meeting, which was scheduled for July 14th at 5:30 p.m., will be rescheduled as it conflicts with the Town Council meeting that same evening. Mark and Preston will pinpoint a date and time for the next meeting to take place and that information will be put out through the Town's communication channels. 
  • Contact info:
    • Brian Kail - 970-596-7147, brian@strykerco.net 
    • Mark Clutts - 970-901-6220, mark@strykerco.net
    • Preston Neill - 970-318-0081, pneill@town.ridgway.co.us